[vc_row][vc_column][vc_media_grid grid_id=”vc_gid:1598408860018-6c394a8e-994c-9″ include=”39292,39295,39293″][/vc_column][/vc_row][vc_row][vc_column][vc_column_text]The manufacturing portion of the Northrop Grumman Launch Vehicles Division HQ incorporated significant outfitting in order to adequately support their $1.1 billion defense contract. This project entailed the construction of a 277,000 SF 2-story manufacturing building to manufacture materials with secure access bays.
In the production facility, Willmeng Construction included:
- 11 five-ton overhead cranes with a 35-foot hook height and 50 feet of clear height in the Integration and Test Phase area.
- A 3’ thick slab reinforced with wide-flange beams and #9 reinforcing bar to withstand up to 10,000 psf.
- The precision in quality control required for this installation resulted in zero re-work after installation.
- Test bunkers were prefabricated with fire sprinklers, lighting, lightning protection grounding, AC and exhaust ventilation.
This project had all the ingredients that make build-to-suit the right answer. Thank you to the Douglas Allred Company, Balmer Architectural Group, and all of our trade partners who made this project a giant success for Chandler and the aerospace industry.[/vc_column_text][/vc_column][/vc_row]